| | search  
   
Metorex Mining Ltd

Company
Overview

  • Growth Projects
  • >
  • Kinsenda Project

Kinsenda Project

 

       
 

Introduction
The Kinsenda copper mine is located in the DRC close to the Zambian border town of Kasumbalesa, and is the focus of a bankable feasibility study (“BFS”) to bring the mine back into production.

Activities over the last 18 months
During the period June 2009 to December 2010, Metorex continued to advance the BFS along with appointed consultants. An infill drilling programme was completed in August 2010, and an updated geological resource model for the western portion of the mine has been completed by Snowden Mining Industry Consultants (“Snowden”). Snowden has recommended a further drilling programme beyond the western section of the mine at 75 metre drillhole spacings to confirm historical drilling and this recommendation is under consideration. A SAMREC-compliant resource of 23 Mt at 4,1 percent copper has been declared as at 31 December 2010.

Snowden has also delivered mining infrastructure and mining method designs for an envisaged ore mining rate of 40 000 tons per month from 270 metres below surface down to an ultimate depth of 600 metres. A backfill study is underway to cater for the drift-and-fill mining method. Metallurgical testwork is ongoing and MDM Engineering is designing a metallurgical plant which comprises conventional crushing and milling followed by flotation of sulphide and oxide copper minerals to produce both sulphide and oxide copper concentrates. Metallurgical test work thus far indicates an overall recovery of copper from run-of-mine ore to concentrate of 90 percent yielding approximately 22 000 tonnes of copper contained per annum.

Metago and rePlan have substantially completed the environmental and social impact assessment (“ESIA”) studies respectively and wet season studies are underway. Golder Associates was appointed to complete the tailings storage facility site selection and design, and this work is substantially completed. Groundwater remains a key risk for the project and mine inflows have been estimated to be between 28 000 m3/d to 45 000 m3/d when the mine is fully developed. The actual inflow will depend on how the aquifers respond to pumping from the deeper levels, and water handling and pumping infrastructure requirements are in planning. Power reticulation studies have also largely been ompleted.

Outlook
The schedule for the BFS shows completion by mid-year 2011 at a total expenditure of US$6,1 million. The feasibility report for the US$130 to US$150 million project is almost complete and has been presented to the DRC authorities whereafter it will be presented to the Metorex Board. Funding of the project will be by way of Metorex cash flows supplemented by US$66 million through debt facilities currently being negotiated with lenders. The details and terms of these arrangements will be announced once finalised with the lenders.

   
       
     
  Growth Projects CPR  
  SUMMARY
 
  View summary here   
  FULL
 
  Download full CPR here   
     
 

 

 
  back to top