| | search  
   
Metorex Mining Ltd

Company
Overview

  • Operations
  • >
  • Chibuluma Mines Plc - Copper

Chibuluma Mines plc – Copper

 

       
 

The introduction of hazard identification and risk assessment, especially before commencing any tasks at the mine, has led to an improvement in most safety-related measures. The introduction of the new integrated SHEC management system for reporting and control has augmented the safety effort. Total lost-time injuries during the six months ended 31 December 2010 (“current period”) remained constant relative to the six months to June 2010 (“June 2010”) at four.

The volume of ore through the plant increased by 12 percent for the current period. This was as a result of improved mining performance, a successful plant debottlenecking process and fewer electrical power interruptions. The mine completed the installation of additional on-site generating capacity towards the end of the period so as to minimise the risk of further electrical interruptions at a capital cost of US$1 million.

 

Copper headgrades decreased for the current period compared to June 2010. This is due to the mining having moved into a close-out area where mining stresses are particularly high causing scaling of the hangingwall and subsequent dilution. This area will be mined out by the end of the first quarter of 2011. Within the usual bounds of variability the ore body grade does improve with depth.

Plant recoveries improved by two percent to 92 percent. Management has focused on improving recoveries and numerous interventions, primarily related to ensuring constant flow through the float plant and improving the crushing circuit, have resulted in good improvements.

Copper produced and sold for the current period increased by three percent to a record 8 990 tons. All copper for the period was sold to the Chambishi Copper Smelters under contract. The terms are more favourable than international pricing after taking into account the newly imposed export tax on concentrates.

On-mine costs per ton milled were well controlled and remained flat at US$59 per ton, assisted by the increased volumes mined and milled. Realisation charges also decreased by six percent per ton sold following less smelter penalties incurred. Stated in terms of cash costs per ton of metal sold, Chibuluma had a credible performance for the current period as costs rose by three percent. The increase in cash costs per ton of metal sold to US$2 932 when compared to June 2010 was due to the lower grades despite the higher volumes mined and milled.

Capital expenditure remained relatively constant and amounted to US$13,3 million as a result of the purchase of new mining fleet vehicles (US$3,2 million) needed to maintain production levels as well as increased capital spend on engineering items required to upgrade the quality of capital equipment at Chibuluma. In addition, Chibuluma commenced with an exploration programme aimed at increasing the life of the mine (US$0,6 million). Mining development remains a large proportion of the capital spending (US$3,5 million). For the current period the Chibuluma Mine increased its cash mining profit by 34 percent to US$47,1 million. This was driven off the back of higher copper production, higher copper prices received and cost control. The average copper price received increased from US$6 436 per ton to US$8 112 per ton.

The Chibuluma Mine is well set to maintain mining and milling volumes in the coming period. Volume restrictions, given the increasing depth of mining and erratic power supply, will be mitigated through careful planning and strategic interventions, and the depth-related increases in grade will assist in maintaining production levels. In addition, the dilution due to the close-out areas should reduce by the end of the first quarter of 2011. Various cost pressures will be experienced during the coming year, mainly in the form of wages, power and diesel costs. Capital expenditure levels are expected to remain similar in the coming year. However, additional expenditure will be incurred on exploration activities targeted at extending the life of the mine.


Key results

Chibuluma Unit Six months
Dec 2010
Six
months June 2010
12 months Dec 2010 12 months June 2010 12 months June 2009
Tons milled (t) 301 659 269 431 571 090 552 051 568 187
Headgrade
– copper
(%) 3,2 3,6 3,4 3,5 3,1
Overall recovery
– copper
(%) 92 90 91 90 90
Copper produced (t) 9 008 8 721 17 729 17 140 15 940
Copper sold
– total
(t) 8 990 8 702 17 692 17 181 15 907
– into hedgebook (t) 3 000 4 200 7 200 7 275
– at spot price (t) 5 990 4 502 10 402 9 906 15 907
– hedgebook price
    achieved
(US$/t) 7 692 5 308 6 301 4 912
– average spot price
    achieved
(US$/t) 8 322 7 488 7 964 7 239 3 876
On-mine cost per ton milled, net of ore
stock movement
(US$/t) 59 59 59 55 52
Copper realisation costs per ton of
copper sold
(US$/t) 924 987 960 946 917
Total cash cost/ton of copper sold (US$/t) 2 932 2 840 2 898 2 783 2 793
Capital expenditure US$’m 13 12 25 18 16
 
       
     
       
  Chibuluma CPR  
  SUMMARY
Competent Persons Report [CPR] for Chibuluma
 
  View summary here   
  FULL
CPR for Chibuluma
 
  Download full CPR here   
 


Management
J Trouw,
General Manager
M Bullock,
Financial Manager
P Jordaan,
Mining Manager
D Olivier,
Engineering Manager
J Sikamo,
Metallurgical & Environmental Manager
M Mwale,
Chief Services Officer
G van Heerden,
Finance Executive

Directors
C Needham
D Castle
J Makumba
D Littleford
M Lumamba



 
  back to top